Project Name: Hillbrook Anglican School – Year 7 Building
Location: Enoggera
To support the transition of Year 7 into high school, Armstrong Building delivered a new purpose-built learning precinct at Hillbrook Anglican School. The project involved the demolition of an existing structure and construction of a large, integrated facility with modern amenities and thoughtful landscaping.
Scope of Works
- Construction of the Year 7 Precinct, including:
- General and specialist classrooms.
- Staff and student bathroom facilities.
- Landscaped outdoor areas with water feature.
- Connection to adjacent buildings to ensure seamless student movement and visual continuity.
Site Management & Coordination
- Careful traffic management planning was critical, with shared access zones serving both construction vehicles and school drop-off.
- Detailed staging to minimize disruption and safeguard student safety throughout the build.
Late-stage Compliance Support
- Guided the client through the design and implementation of a fire booster pump system to satisfy QFRS certification.
- Despite its late inclusion, the system was delivered without affecting program milestones.
Outcome The completed Year 7 Building now stands as a tailored learning environment that enhances school capacity and cohesion—delivered on time, on budget, and in full compliance.